Construction Update
it’s moving fast! August is coming.
Can you feel it? We can! PIckle at the Palms is coming! May was a very busy month for the Sellen team, and the building is really starting to come to life on the inside (and the outside too)! We’re often asked if the building will really be done in August, and the answer is a resounding YES. This past week alone, Sellen had between 50-70 people on site working at any given time. That’s a lot of talented tradespeople!
The first photo below gives a nice snapshot of the upper level of courts while walking down the corridor between the courts. In this photo you can see the fence posts that will be the stabilizing source of fencing around each court, and you can also see pads on the building’s columns. The lights shining toward the camera are construction lights (not permanent). In the second photo, the permanent lighting is being installed. Court illumination has been designed to provide diffused light with zero glare and excellent play visibility. Think light + bright!
The third photo also highlights the acoustical panels that cover the ceiling of both levels of courts. These are the 8 foot long gray panels you see recessed in the ceiling. The acoustical engineers spent a significant amount of time considering the happy sound of pickleballs at play. The result? The acoustical panels at The Palms will dampen that pinging sound by over 50%. Happy ears!
The fourth photo gives a good look at the gray pads that cover the walls adjacent to the courts. Yes you CAN do that ATP at The Palms! Below you’ll discover The Palms parking lot, gearing up for pavement. Hooray for over 50 free parking spots!
And hey, check out the lobby and Pro Shop! It’s really coming along. In the sixth photo you can see the entry doors, the front desk under construction and a portion of the shelving for Palms branded merch, paddles, gear and more!
Looking ahead: Court surfacing is underway! Creating the courts involves the application of many layers. So it will take a bit before the courts start looking like courts! The appliances for Mainstay Provisions at The Palms are being moved into place, and plumbing fixtures will be installed. June brings us another month of precise coordination and forward movement for Team Sellen: exactly what they are good at! We’re getting really close!